Die Techniker von Varian setzen ihr Fachwissen und ihre Erfahrung dafür ein, unsere Systeme schnell, effizient und umfassend einzurichten. Auf ihr Fachwissen kann man sich in unserem gesamten Leistungsspektrum verlassen. Dadurch, dass Updates und Behandlungen beschleunigt und auf dem richtigen Weg gehalten werden, ermöglicht Varian den Kliniken, sich auf eine effiziente Patientenversorgung zu konzentrieren.

Customer Success Stories

  • Challenging delivery

    Kaiser Permanente Los Angeles Medical Center, Los Angeles, USA
    Halcyon system was to be delivered through a parking garage that had a low ceiling, with an uneven slope downhill. Machine was delivered with no damage after months of reviewing the rig path and successful collaboration with Site Planning and Project Management.
  • Full remote software upgrade

    Unidad de Radioterapia Oncológia Gurve, Caracas, Venezuela
    Complex Software upgrade project requires extensive planning and alignment with the customer. The partnership and collaboration between the project teams resulted in a remarka-ble project executing the first ARIA OIS for radiation oncology v16.1 fully remote upgrade globally.
  • Installation of new generation systems

    Lagos University Teaching Hospital, Lagos, Nigeria
    By replacing an old linac and adding two more systems, NLCC (NSIA-LUTH Cancer Centre) has become the biggest and busiest cancer treat-ment center in West Africa. Varian‘s teams worked diligently with authorities and staff to deliver and install three latest generation systems: two VitalBeam radiotherapy system and one Halcyon.
  • Full system Installations at multiple sites

    Amsterdam UMC, VUmc/AMC, Amsterdam, The Netherlands
    Six Ethos Therapy systems installations at three different locations performed during the pande-mic. First customer worldwide to connect several Ethos systems at multiple locations to one Server Appliance system.
  • Tight project scheduling

    Cancer Hospital Ahmedabad, Ahmedabad, India
    Despite a very challenging bunker design and tight project schedule, this Halcyon was delivered and installed within a very short period. In just 27 days after delivery the first patient received their first treatment.
  • Linac replacement and vault renovation

    Queen Mary Hospital, Hong Kong, China
    Upgrade from an older Clinac iX system to a TrueBeam radiotherapy system required a careful evaluation of all radiation protection requirements. The Varian team in collaboration with the customer developed an implementation solution without causing any delay in the project schedule and disruption of the department’s workflow.
 

SuperFast Installation

Wir begrenzen die Ausfallzeiten des Behandlungssystems von der Linac-Entfernung bis zur Installation des Neugeräts auf 2 bis 3 Wochen.

 

Smart Step

Wir minimieren Störungen vor Ort durch die Koordinierung, Planung und Sequenzierung von Software-Upgrades.

 

Weekend OBI

Sie erhalten neue Behandlungssystem-Technologie, ohne dass Bestrahlungstermine Ihrer Patienten verschoben werden müssen.